** US129 PAVING UPDATE **

A start date has been established for the repaving of the 11 miles section of US129 known as Tail of the Draon. The goal is to start paving the first week of May, but could be pushed out a week or so.

The plan is to to pave and perform necessary lane closures during daylight hours MONDAY thru THURSDAYS.

Paving will begin in the southbound direction and finished at the TN/NC state line The paving must be completed within 35 calendar days of the start date. So ideally the paving will be complete sometime in mid to late June.

Starting the week of April 22, TDOT will begin installing construction signs and some guardrail replacement. 

Please check here and our social media for updates, we will post when construction begins.